Navigating Heat Pump Retrofits - A Guide for Facility Managers

April 30, 2024

A lot has changed since we released our first Advisory Note on heat pumps back in 2018. Increasingly, building owners are no longer asking if heat pumps should be installed to replace fossil fuel-fired heating technology, but instead are asking when – and how.

With the prevalence of Net Zero commitments among building asset holders, and with the often-quoted target year of 2030 rapidly approaching, Facility Managers are now being tasked with planning and executing this technology transformation – and there are many technical aspects they need to consider.

This Advisory Note provides Facility Managers with key considerations and recommended actions needed to navigate heat pump retrofit projects successfully.

Plan Ahead

The most challenging time to effectively plan a heat pump retrofit is when your building’s gas-fired boilers or domestic hot water (DHW) systems have failed
– or are about to.  A heat pump retrofit is rarely as straightforward as swapping out a gas boiler for an equivalent capacity heat pump; even if this approach were technically feasible, the building owner may be paying a hefty cost premium for such a solution.

Facility Managers should plan ahead by ensuring that building asset registers are up to date, and there is a good understanding of when the service life of gas-fired plant is forecast to expire. It is also essential to be mindful of any Net Zero target dates or interim target dates by which site degasification is required to occur.

Working backwards from these milestones, allows adequate time for the additional feasibility and engineering exercises required to find the right solution for the building, and to set an appropriate project budget. These tasks could include preparation of a business case, a feasibility study or options analysis, and an implementation plan, over and above the standard detailed design and tendering processes. Also be mindful of the supply lead times for heat pumps, which may be longer than those that Facility Management teams would be accustomed to for gas-fired units.

BMS Data Trend

The correct sizing of heat pump plant is key to ensuring the feasibility and success of a heat pump retrofit project, and it can be a complex engineering task. One of the best ways a Facility Manager can support their engineering team with this task is with the provision of suitable Building Management System (BMS) trend data.

Heat pumps are more expensive on a $/kW basis than the gas-fired equipment they will be replacing – not just in terms of their unit supply cost, but also in terms of the cascading effect on related services infrastructure upgrades (such as electrical infrastructure) that may be initiated by their installation.

Sizing heat pumps simply to match the existing boiler kW capacity may attract a significant cost premium, particularly where existing boilers are oversized (which is not uncommon).

Utilising historical Building Management System (BMS) trend data on metrics such as the annual building heating load profile, field Heating Hot Water (HHW) temperatures and building warm up times will greatly aid the design process, ensure that heat pumps are not oversized, which will also improve the accuracy of future cost and emissions impact calculations.

The Facility Manager can play a pivotal role here by engaging early with the incumbent BMS contractor to address the following questions:

  • Are the relevant HHW or DHW system points being monitored and trended by the BMS?
  • Are field sensors and meters calibrated and correctly interfaced to the BMS?
  • Does the BMS incorporate a calculation of heating kW demand?
  • Is there adequate trend history stored (ideally, multiple years of data could be accessed) and are trending intervals short enough (hourly rather than daily)?

These are questions that the Facility Managers can and should address as early as possible in the project planning stages.

How old are your Switchboards?

When considering the electrical infrastructure to support a heat pump retrofit project, the capacity of the supply transformer and incoming mains to the building may be front of mind. However, it is also vital to understand how the age and condition of the building’s main switchboard itself could affect the project scope and cost. This is in part due to the application of the current Standard for switchboard assemblies (AS/NZS 61439 Low-voltage switchgear and control gear assemblies, Part 1: General rules) which effectively means that modifications to older switchboards, such as creating new submains to serve heat pumps, are significantly more onerous than was the case when the previous standards applied prior to May 2021.

We have a dedicated Advisory Note to provide Facility Managers with additional guidance on this topic.

Having a suitably qualified electrical engineer (ideally in conjunction with a Licensed Electrical Inspector) assess the age and condition of your switchboards, and their suitability for modification to suit a heat pump retrofit project, will ensure a more accurate understanding of the potential scope and costs involved.

Roof Space

Whether used for air-sourced heat pumps, rooftop solar photovoltaics or for other technologies, maximal utilisation of open-air rooftop plant space is increasingly playing a central role in high performance sustainable buildings and can be a determining factor in establishing the feasibility of a heat pump retrofit project.

Facility Managers can assist here in a variety of ways:

  • By planning the removal of any redundant equipment;
  • By assessing whether existing plant layouts can be rationalised
    or reconfigured in a more space efficient way;
  • By assessing whether Building Maintenance Units (BMUs) are still the best maintenance option for the building facade, given the significant physical footprint BMUs and their associated tracks occupy;
  • Through commissioning structural engineering reviews to
    determine potential locations of plant platforms; and
  • By ensuring that the roof condition is well maintained and any required water proofing remediation works are undertaken well ahead of future plant installations.
Performance Testing

Testing the performance of the existing heating infrastructure at lower HHW design temperatures, particularly during morning warm-up conditions, can be greatly beneficial to informing on a future heat pump design.

This is in part due to the fact that many commercially available heat pumps generate lower HHW temperatures than the gas-fired boilers they need to replace; therefore, if the building can still effectively meet its heating demands using lower temperatures, then more heat pump model options are available
for consideration.

Consider engaging the incumbent BMS contractor to run such performance tests during non-occupied periods, with test procedures developed by a suitably qualified Consultant.

Consider Staging Electrification Works

Undertaking 100% base building electrification works as a single “year 1” project could be perceived as cost-prohibitive by asset owners, resulting in electrification works continually being delayed into the future.

Early execution of preliminary electrification works, potentially starting with DHW system electrification or undertaking the first of a series of staged HHW electrification projects, will give the Facility Management team practical experience in executing heat pump retrofits and familiarisation with the technology involved, helping to ensure that meaningful emissions reduction plans do not stall, and can contribute to any interim emissions reduction targets required as part of Net Zero commitments.

It is helpful to consider that some of the most efficient heat pump units currently on the market are modular in design, allowing for expansion of thermal capacity within a relatively compact physical footprint and without requiring extensive modification works.
These systems are particularly suitable to staged electrification upgrades and should be considered by the design teams.

Take Advantage of Tenant Vacancies

No building owner likes having a vacant tenancy. However, these may provide a valuable opportunity to complete on-floor modification works that are required under certain heat pump retrofit projects. These can include; replacing floor-by-floor Air Handling Units (AHU) HHW coils or Variable Air Volume (VAV) reheat coils, or accessing HHW risers, without disrupting building operations. Take advantage of any known upcoming vacancies and plan accordingly.

Compare Lifecycle Costs

Comparing installation cost estimates for a heat pump retrofit project against a boiler replacement, or even between various heat pump retrofit options, without also accounting for full lifecycle costs, does not provide an accurate basis of comparison and may incorrectly convey project infeasibility.
Ensure that any feasibility assessments performed provide the Facility Management team with a lifecycle cost and emissions comparison (e.g. over a 20- or 25-year period), and factor in considerations such as modelling the comparative escalation of fuel and electricity costs, anticipated ongoing maintenance costs, emissions benefits afforded from procuring 100% renewable power, and costs associated with carbon offsetting of continued gas usage and refrigerant leakage.

Other Items to Consider
  • The location of existing boiler plant and main HHW pipe headers (potentially in basement levels) versus the likely location of
    air-sourced heat pumps (rooftop areas), and the implications this may have on requiring new HHW risers.
  • The acoustic performance of air-sourced heat pumps providing heating to 24/7 operational areas, in consideration of relevant legislative guidelines (e.g. EPA guidelines).
  • Heat pump refrigerant type implications including carbon emissions reporting (deemed or reported refrigerant leakage forms part of a building’s Scope 1 carbon emissions) and the various refrigerant types have been differing equivalent carbon emissions), or plant room design and configuration (based on the refrigerant type’s particular flammability rating).
  • Funding mechanisms, including green financing options or accessing government rebates.
Resources

There are excellence resources available for Facility Managers that address the items raised here; we have highlighted the key ones below:


For further guidance on how to navigate a heat pump retrofit project, please contact:

Andrew Nagarajah
Senior Engineer – Sustainability
A.G. Coombs Advisory

+61 3 9248 2799
anagarajah@agcoombs.com.au

For more information

Contact Us

Loading ratings...

Latest Advisory Notes

June 24, 2024 in Advisory Notes

Mould in Buildings and HVAC Systems

Mould plays an important role in the natural environment as a break-down mechanism for dead organic matter. In the built environment it is an unwanted...